Construction progress in our diary

We are implementing a PV project with an installed capacity of 48 Megawatt in Deubach in the northeast of Baden-Württemberg, Germany. After completion, almost 89,180 modules will convert sunlight into electricity. An area of 380,000 square meters, or the equivalent of 53 soccer fields, will produce enough green electricity to meet the annual needs of around 15,000 households.

48000

kWp installed capacity

89180

modules

380000

square meters
Layout Deubach

Special Features of the Solar Farm

The terrain of the construction area is challenging, as a slight north-south gradient is joined by a strong west-east gradient in one of the fields. In addition, BELECTRIC is building a separate substation for the power supply.

To promote biodiversity, numerous measures are being implemented, including the use of a special seed for the field larch.

A novelty: BELECTRIC will also take over the asset management for Deubach solar farm and add the solar plant to its own company portfolio.

Deubach

2023
Construction of the transformer station is in full swing

Construction of the transformer station is in full swing

The construction of a separate transformer station is necessary for the electricity feed-in.

The pile driving works have begun

The pile driving works have begun

From now on, the substructure is being fixed into the ground. The construction progress is then measured during drone flights.

Spatenstich Solarpark

Construction site opened by groundbreaking

A first milestone has been reached. The construction work can now officially start.

Construction of storage area and site path are in full swing

Construction of storage area and site path are in full swing

Preparations for the start of construction include the construction of storage areas and auxiliary roads for logistics.

The area is ready for the start of construction

The area is ready for the start of construction

Preparations for the start of construction are already in full swing. The construction site in Deubach is also ready for use and is just waiting for the groundbreaking ceremony.